The Norwood Mobility Project
The Norwood Mobility Plan was adopted by Council on February 24, 2026 (Resolution # 2026-0043). Thank you for all your support and participation in developing a vision to improve safety and mobility for all modes of transportation on Norwood Avenue.
open_in_full
The Norwood Mobility Plan
The Norwood Mobility Final Plan (Adopted by Council 2/24/26; Reso# 2026-0043)
Project overview
Norwood Avenue between Main Avenue and Arcade Creek is a critical corridor serving local neighborhoods, as well as students and businesses. However, it is part of the City’s High Injury Network, corridors with a high number of transportation related severe injuries and fatalities, and identified as a high priority project in the City’s Transportation Priorities Plan.
The City was awarded a competitive planning grant to review data and work with the community to develop a plan to address safety and mobility on the corridor.
The goal of the plan is to identify a data driven, community supported vision for a future Norwood Avenue, inclusive of all users and reflective of the needs of the community it serves, eliminating barriers to jobs, housing, and services.
Having a Council adopted plan ensures the City is eligible for competitive grant funding for any next phases such as Preliminary Engineering Design, Environmental Clearance, Final Design and Construction.
open_in_full
Project schedule
Fall-Winter 2024: Existing conditions analysis
Fall-Winter 2024: Community engagement phase 1, including in-person and virtual community workshops, and community pop-ins
Spring/ Summer 2025: Alternatives analysis
Summer 2025: Community engagement phase 2, including community survey, virtual and in-person community workshops, and community pop-ins
Summer/ Fall 2025: Community input evaluation and development of Public Draft Plan
Fall 2025: Community Engagement Phase 3: Public review of Draft Plan
Winter 2025/26: Final Draft Plan to Council (Adopted February 24, 2026)
open_in_full
Project documents
Norwood Mobility Plan Public Draft presented for public comment Oct 10- Nov 2
Overview of proposed design alternatives for public review in Phase 2