Vision Zero School Safety Project

Construction Update - November 2026

Construction activity near The Met High School – 810 V Street, Sacramento – is anticipated to be completed on November 6.

Crews are currently completing pedestrian and roadway improvements near William Land Elementary School on 12th Street, between U and V Streets. Work hours are 9:00 a.m. to 4:00 p.m., with completion anticipated during the week of November 9.

Construction near West Campus High School on 58th Street is scheduled from November 6 – 20, between 8:30 a.m. and 3:30 p.m. Work includes pedestrian and roadway improvements, including a new median island at the Fruitridge Road and 58th Street crosswalk.

Signs, flaggers, barricades and cones will be in place to help guide drivers and pedestrians through the areas. Please move through the areas with care.

Questions?

Call/Text: (916) 245-0430
Email: vzconstruction@cityofsacramento.org

Frequently Asked Questions

When will work occur? *

 The Met High School: October 26 - November 6, 2026
 William Land Elementary School: November 2 - November 12, 2026
 West Campus High School: November 6 - November 20, 2026

*subject to change, weather dependent 

 

What kind of work will occur?

The Met High School: Installing detectable warning surfaces at sidewalk corners, updating crosswalk and roadway striping, and improving the bus stop area by reconstructing the sidewalk and concrete pads.

William Land Elementary School: Reconstructing sidewalks and curb ramps, installing detectable warning surfaces at sidewalk corners, updating crosswalk striping, and adding new roadway striping.

West Campus High School: Refreshing and updating crosswalk and roadway striping, installing a median island through the crosswalk on Fruitridge Road and 58th Street.

 

2027 Construction Areas

2027 construction areas will include:

  • Natomas High School 
  • Smythe Academy of Arts and Sciences 
  • St. Hope Public School 
  • Father Keith B. Kenny Elementary School

 

For an interactive Google Maps, please click here for the following link. 

Project Background

The Vision Zero School Safety Project is part of the City of Sacramento’s ongoing effort to improve safety for people walking, biking and traveling near schools.

The improvements are based on recommendations from the City’s Vision Zero School Safety Study, which evaluated safety and access conditions near 20 Sacramento schools. Recommendations were developed through technical evaluations and consultation with school communities.

The project is intended to make travel to and from school safer and more comfortable for students, families and others traveling near these campuses.

Project Funding

Funding for this project includes $1.7 million in federal Community Project Funding and $550,000 from the City of Sacramento’s Major Street Construction Fund.

Questions?

Call/Text: (916) 245-0430
Email: vzconstruction@cityofsacramento.org

ON THIS PAGE