Stockton Blvd Plan Project Overview

About the Stockton Boulevard Plan

The City of Sacramento’s new Neighborhood Development Action Team (NDAT) is starting a plan to revitalize Stockton Blvd and surrounding neighborhoods while benefiting existing residents and businesses. We are looking to partner with residents, business owners, landowners, and organizations as we look for ways to strengthen the corridor as a vital core for the surrounding neighborhoods and increase the local community’s ownership of housing, land, businesses, and investments.

Schedule of ActionsNotes

1. Inventory

Fall 2020 - Winter 2021

Review and analyze existing conditions.

2. Issues & Priorities

Fall 2020 – Winter 2021

Identify blind spots, focus points, issues, challenges, opportunities, and priorities.

3. Visioning*

Winter 2021 - Spring 2021

Create a shared vision and define community success.

4. Strategies*

Spring 2021 - Fall 2021

Develop and prioritize actions.

5. Create Draft Plan*

Fall 2021 - Summer 2022

Review input and draft documentation.

6. Community Working Version*

Summer 2022 - Summer 2023

Discuss initial draft and collect updates and ideas.

7. Update Plan

Fall 2022 - Summer 2023

Review input and update draft document.

8. Public Review Draft Plan/EIR*

Fall 2023 - Spring 2024

Release Public Review Draft Plan and Environmental Impact Report and collect input.

9. Adopt Plan

Summer 2024

Finalize and adopt the Stockton Blvd Plan and certify the EIR.

  * Major Public Engagement Phase